- Initial Information
- Material Selection
- Offer Letter (NDA)
1 week
- Site Survey
- Final Design
- Signing PPA Contract
- Technical & Transaction Checklist Documents
1 week
- Hire a third-party (Architects & Engineers) with sufficient capacity to assess the structure before installing the solar system
1 week
- Approval for Licenses/Permits
- Prepare Materials and Components
1 week
- Installing Solar Panels
- Constructing Substation
- QA/QC
- No Interruption
- Best Security
8 week
- Trial Operation
- COD